Overhauls / Field note

Hot gas path inspection: the 12-week parts plan

9 min readNEGBUY Outage Support · Outage planning
Gas turbine engine on a maintenance stand
Gas turbine engine on a maintenance stand

The HGP itself is a two-week job. The other ten weeks are drawings, serial numbers, inspection findings and shipping — and that is where outages actually overrun.

A hot gas path inspection is defined by the twelve-week window that surrounds it. The physical work — removing combustors, inspecting transition pieces, pulling stage 1 and 2 buckets, checking shrouds and seals — is well understood by any competent crew. What decides whether the unit returns on the contracted date is how the parts pipeline was organised before the first bolt moved.

Weeks −12 to −9: lock the configuration

Start with documentation, not with a shopping list. The rotor assembly drawing, the combustor can serial numbers and the last set of inspection reports together define what is actually installed. Frames get retrofit over a forty-year life; two otherwise identical units in the same plant often carry different bucket generations.

  • Collect frame model, unit serial, and every bill of material for hot-section components
  • Confirm each installed part number against the assembly drawing, not against a previous purchase order
  • Ask for the repair-versus-replace limits in writing before you scope the parts

Weeks −9 to −6: scope and quote

This is the longest single phase because it is where engineering and procurement disagree. Repair limits decide how much of the bucket set can be re-used, refurbished, or replaced. Ask for a written disposition matrix: for each component, the limit, the inspected condition, and the resulting action.

The outage that goes wrong is the one where the crew opened the machine before anyone had confirmed what the spares list assumed.

Plant maintenance manager, refinery cogeneration

Weeks −6 to −2: order and expedite

ItemTypical lead timeOrder by
Stage 1 buckets, new16–28 weeksprevious outage
Stage 1 buckets, refurbished exchange6–10 weeks−8 weeks
Transition pieces10–18 weeks−10 weeks
Combustor liners and caps8–14 weeks−9 weeks
Seals, gaskets, fasteners2–5 weeks−4 weeks

Anything in the 16-week-and-over band cannot be recovered by expediting. If stage 1 buckets are on the list and the inspection is eight weeks away, the honest answer is that this outage runs on refurbished exchange hardware and the new set lands for the next one.

Weeks −2 to 0: stage the site

  • Kit the parts by machine location, not by supplier — one crate per combustor position
  • Attach the disposition matrix to the crate lid so the crew is not re-deciding anything
  • Confirm lifting gear, cradle positions and rotor stand clearances against the actual bay
  • Brief the NDE subcontractor for the final blade-root and wheel-space inspections

The return-to-service week

Budget three days after the machine closes: alignment checks, boroscope verification of clearance, and the first start's vibration and exhaust spread data. That last dataset becomes the clean baseline for the next interval's heat-rate trending, so capture it properly rather than photographing the screen.

  • HGP
  • Outage
  • Combustion
NEGBUY Outage SupportOutage planning — NEGBUY Group
Talk to the desk
07 / Start a conversation

SEND THE
PART NUMBER.

Tell us what's down, what's worn or what's due — we'll come back with a scoped fixed quote and a real dispatch date.

  • 24 h quote turnaround
  • 48 h emergency dispatch
  • 12 mth parts warranty
contact@negbuy.com

Typical reply within one business day. No obligation.